Over the next four to six weeks the glass infill which will link the upper forecourt to the Switch House will be installed. During this period the builders will finalise any work to the Switch House doorways.
The Museum’s Workshop staff are building and installing the shelving units for the new shop. The drawings for the cafe are completed and have gone out to tender. As previously reported it is intended that these commercial outlets be installed and opened prior to Christmas.
Now that the major phase of work is nearing completion the Museum is also undertaking the refurbishment of the toilets on level 2. This work is also scheduled for completion by December 2012.