External work
Level 3 forecourt – Work continuing on the forecourt includes: levelling of steps and installation of tactiles. Handrails and glass balustrades will begin to be installed in the week commencing 16 April. Builders will also generally clean and remove items from the forecourt.
Internal work
Level 2 – installation of new doors continues; area to be cleaned and tidied up
Level 3 – continue with patching and paint touch ups
Level 4 – Sanding and filing of the balustrades continues. Top of beam to be painted.
Level 5 – Sanding and filing of the balustrades continues. Top of beam to be painted.
Visitors lift – removal of protective coating and cleaning to be undertaken
Sprinkler heads – installation of ‘fast response sprinkler’ heads continues throughout the Museum.