External work
Level 3 forecourt – Work continuing on the forecourt includes: levelling of steps; installation of pavers along the steps of the Macarthur Street side and installation of tactiles handrails. Waterproofer will return to undertake more work on Tuesday 27 March. Builders will also generally clean and remove items from the forecourt.
Internal work
Level 1 – re-installing magna grid continues
Level 2 – continue to reinstall amenities; waterproofing in the storage area; installation of new doors continues
Level 3 – continue with patching and paint touch ups. Handrail installation to ramp will take place on Wednesday.
Level 4 – Sanding and filing of the balustrades continues. Rendering on top of beam to be smoothed out. Beam to be painted – exact date to be confirmed.
Level 5 – Sanding and filing of the balustrades continues. Rendering on top of beam to be smoothed out – exact date to be confirmed.
Visitors lift – installation of trims and sealing continues
Sprinkler heads – installation of ‘fast response sprinkler’ heads continues throughout the Museum.