External work on the forecourt
- Glass balustrades on stairway – work continues
- Harris Streetsteps – levelling to be completed this week
- Installation of hand rails and lighting – hand rails have been installed. Installation of light fittings in the hand rails – date to be confirmed.
- Tactiles and nozing strips – will continue to be installed
- Paving – ongoing work to level pavers is continuing
- Installation of bubbler – date to be confirmed
Installation of glazing strip and barriers – design is being finalised, estimate work will commence in 2 to 3 weeks time.
Internal work
Basement work – is completed
Level 1 – back glass panel to be replaced on visitor lift – date to be confirmed
Level 2 – (1) handles and hardware to be installed on new doors in the storage area (2) back glass panel to be replaced on visitor lift – date to be confirmed. (3) Area to be tidied up.
Level 3 – wall to be constructed
Level 4 – wall to be removed
Level 5 – work is completed
Visitors lift – the lift will be closed for a day for thorough cleaning internally and externally. Dates for this work to be confirmed.
Defect list – builders are going through the defects list and rectifying any work required.

